The project team is working to create a new Web site for the company. The Web site is the _____.
a. deliverable
b. requirement
c. stakeholder
d. milestone

Respuesta :

exceloffcity
exceloffcity exceloffcity
  • 02-11-2018

B. The requirement :/

Answer Link

Otras preguntas

What Leonardo da Vinci’s technique of sfumato allows a painter to:?
There are 130 m&m's in a bag. there are half as many green as red. the number of blue is equal to the number of red and green combined. there are half as ma
Why do you think spain joined with venice and other italian states in the battle of lepanto?
I need help in number 2 ASAP please
How much time needs to pass for an ar account to be considered delinquent?
A healthy weight for an individual should not be based exclusively on weight, but on: select one: a. amount of lean body tissue. b. energy intake versus energy
Need y’all help. What are 3 things that Ben Franklin did that helped with medicine/ science?
Explain two contrasting Muslim teaching about sadaqah (charity)
The student center on campus has burritos, bagels, or burgers for lunch, and they all cost the same. you decide to have a burger today, but if they were out of
Keywords Define each term: 1. Author’s purpose: Type your answer here. . 2. Chronological order: Type your answer here. 3. Conflict: Type your answer here