When looking at a program board at the end of program increment (PI) planning, what does it mean when a feature is placed in a team's swim lane with no strings

Respuesta :

IfeanyiEze8899 IfeanyiEze8899
  • 04-01-2021

Answer:

It simply means that other teams can independently complete the feature.

Explanation:

PI or program increment is a planning interval during which an agile release train (ART) plans and produces working and tested software and systems. It takes a duration of 8 to 12 weeks

Agile teams can access and independently complete various ARTs found in their swim lanes with no strings.

Answer Link

Otras preguntas

What was a result of middle-class Americans moving to the suburbs of most cities?
What is the approximate value of 120 degrees in radians?
if two cars are identical except for the size of their engines, how will that affect their performance on the highway?
40,___,37 1/2,36 whats the missing number help!!
A _____ is a new substance formed in a chemical reaction. a. catalyst b. reactant c. product d. coefficient
practice 2 digital subtraction 5 0 _ 1 8
Justin gave the clerk $20 to pay a bill of $6.57. How much change should Justin get?
Which type of election is not accurately described? A) In a primary election, candidates are nominated for office. B) In a general election, national or s
The main purpose of a balance sheet is to _____. comply with IRS laws obtain a bank loan show a business's financial state show profits earned
After germination, continued plant growth pushes first the shoot and then leaves through the soil. We would expect the emergent leaf cells to contain many _____